Home >> Chevrolet >> 2005 >> Aveo Base, 4D Hatchback >> Repair and Diagnosis >> External Pages >> Different variant/trim >> Section 3 (Automatic Transmission - Removal & Installation, Service, Overhaul, Troubleshooting & Diagnosis) >> Repair Instructions >> Shift Solenoid (1, 2), Timing Solenoid, Lock-Up Solenoid Inspection

Shift Solenoid (1, 2), Timing Solenoid, Lock-Up Solenoid Inspection

WARNING: This page is about a different variant/trim than selected.
    Fig 1: Inspecting The Resistance Of Each Shift Solenoid Between The Terminal & Ground
    GM1245799Courtesy of GENERAL MOTORS CORP.
  1. Inspect the resistance of each shift solenoid between the terminal and the ground.
  2. Fig 2: Minimum & Maximum Resistance Plot Lines (Shift, Timing & Lock-Up Solenoid)
    GM1245800Courtesy of GENERAL MOTORS CORP.
    IMPORTANT: The resistance of the solenoid can become infinity ohm when the resistance measurement is made at high temperatures.
  3. If the resistance value is not between the minimum and maximum resistance plot lines, then measure the solenoid resistance at 20°C (68°F).
  4. Fig 3: Testing The Operation Of Shift Solenoid
    GM1245801Courtesy of GENERAL MOTORS CORP.
  5. Test the operation of the shift solenoid. The shift solenoid is a normally open solenoid. Air will only pass through the solenoid when it is not energized.
  6. Apply compressed air to the solenoid inlet.
  7. If the solenoid does not allow air to pass thought the solenoid, replace the solenoid.
  8. Apply B+ and Ground to the solenoid.
  9. If the solenoid allows air to pass through the solenoid, then replace the solenoid (1).
  10. Fig 4: Testing The Operation Of Timing Solenoid
    GM1245802Courtesy of GENERAL MOTORS CORP.
  11. Test the operation of the timing solenoid. The timing solenoid is a normally closed solenoid (2). Air will only pass through the solenoid when the solenoid is energized.
  12. Apply compressed air to the solenoid inlet.
  13. If the solenoid allows air to pass through the solenoid, then replace the solenoid.
  14. Apply B+ and Ground to the solenoid.
  15. If the solenoid does not allow air to pass thought the solenoid, replace the solenoid.