Installation Procedure
WARNING: This page is about a different car, the 2004 GMC Sierra, 2004 GMC Cab & Chassis Sierra, 2004 Chevrolet Silverado, and 2004 Chevrolet Cab & Chassis Silverado. However, it is still accessible from the selected car via links, so may be relevant.
- Install the service disconnect power cable (2) to the HCC and service disconnect switch.
- Install the service disconnect power cable nuts (1) to the HCC and the service disconnect switch.
Tighten: Tighten the nuts to 10 N.m (89 lb in).
- Install the ESB intermediate cover. Refer to Energy Storage Box (ESB) Trim Cover Replacement (5.3L Engine w/RPO HP2) .
IMPORTANT:
Ensure that the power cable is installed to the negative side of the HCC.
NOTE:
Refer to Fastener Notice
in Cautions and Notices.