Installation Procedure
WARNING: This page is about a different car, the 2002 GMC Sierra, 2002 GMC Cab & Chassis Sierra, 2002 Chevrolet Silverado, and 2002 Chevrolet Cab & Chassis Silverado. However, it is still accessible from the selected car via links, so may be relevant.
- Install the lower ball joint (2) to the vehicle.
- Install the bolts (2) retaining the lower ball joint (3) to the steering knuckle. Tighten the bolts to 110 N.m (81 ft lbs).
- Install the lower ball joint pinch bolt (1). Tighten the bolt to 230 N.m (169 ft lbs).
- Install the snap ring (2) to the lower ball joint.
- Install the bolt (8) and nut (2) retaining the bracket to the axle. Tighten the retaining bolt and nut to 25 N.m (18 ft lbs).
- Install the tire and wheel.
- Lower the vehicle.
- Perform a four wheel alignment. Refer to SPECIFICATIONS .