Deployment Inside Vehicle - Vehicle Scrapping Procedure

WARNING: This page is about a different car, the 2004 Pontiac Sunfire and 2004 Chevrolet Cavalier. However, it is still accessible from the selected car via links, so may be relevant.
CAUTION: Refer to SIR Inflatable Module Deployment Outside Vehicle Caution in Cautions and Notices.

Deploy the inflator modules inside of the vehicle when destroying the vehicle or when salvaging the vehicle for parts. This includes but is not limited to the following situations:

  1. Disable the SIR system. Refer to SIR Disabling and Enabling Zones .
  2. Put on safety glasses.
  3. Remove all loose objects from the front seats.
  4. Disconnect the inflatable restraint steering wheel module coil connector.
    Fig 1: View Of Inflatable Restraint Steering Wheel Module Coil Connector
    GM202110Courtesy of GENERAL MOTORS CORP.
  5. Cut the steering wheel module coil harness connector out of the vehicle, leaving at least 16 cm (6 in) of wire at the connector.
    Fig 2: Cutting The Steering Wheel Module Harness To Size
    GM39392Courtesy of GENERAL MOTORS CORP.
  6. Strip 13 mm (0.5 in) of insulation from each of the connector wire leads.
  7. Cut two 4.6 m (15 ft) deployment wires from a 0.8 mm (18 gage) or thicker multi-strand wire. These wires will be used for the steering wheel module deployment harness.
    Fig 3: Deployment Wires
    GM39390Courtesy of GENERAL MOTORS CORP.
  8. Strip 13 mm (0.5 in) of insulation from both ends of the wires cut in the previous step.
  9. Twist together one end from each of the wires in order to short the wires. Deployment wires shall remain shorted, and not connected to a power source until you are ready to deploy the inflator module.
  10. Twist together one connector wire lead to one deployment wire.
    Fig 4: View Of Twisted Connector Wire To Deployment Wire
    GM39393Courtesy of GENERAL MOTORS CORP.
  11. Inspect that the previous connection is secure.
  12. Bend flat the twisted connection.
    Fig 5: Bending The Twisted Connection Flat & Insulating With Tape
    GM39408Courtesy of GENERAL MOTORS CORP.
  13. Secure and insulate the connection using electrical tape.
  14. Twist together, bend, and tape the remaining connector wire lead to the remaining deployment wire.
    Fig 6: View Of Insulated Connector Wire To Deployment Wire
    GM39414Courtesy of GENERAL MOTORS CORP.
  15. Connect the deployment harness to the steering wheel module coil connector.
    Fig 7: View Of Inflatable Restraint Steering Wheel Module Coil Connector
    GM202110Courtesy of GENERAL MOTORS CORP.
  16. Route the deployment harness out of the driver side of the vehicle.
  17. Disconnect the inflatable restraint I/P module connector.
    Fig 8: View Of Inflatable Restraint I/P Module Inline Connector
    GM202118Courtesy of GENERAL MOTORS CORP.
  18. Cut the I/P module harness connector out of the vehicle, leaving at least 16 cm (6 in) of wire at the connector.
  19. Strip 13 mm (0.5 in) of insulation from each of the connector wire leads.
    Fig 9: Stripping Connector Wire Lead
    GM263002Courtesy of GENERAL MOTORS CORP.
  20. Cut two 4.6 m (15 ft) deployment wires from a 0.8 mm (18 gage) or thicker multi-strand wire. These wires will be used for the I/P module deployment harness.
    Fig 10: Deployment Wires
    GM39390Courtesy of GENERAL MOTORS CORP.
  21. Strip 13 mm (0.5 in) of insulation from both ends of the wires cut in the previous step.
  22. Twist together one end from each of the wires in order to short the wires. Deployment wires shall remain shorted, and not connected to a power source until the inflator module is ready to be deployed.
  23. Twist together one connector wire lead to one deployment wire.
    Fig 11: Twisting Together Connector Wire Lead To Deployment Wire
    GM263005Courtesy of GENERAL MOTORS CORP.
  24. Inspect that the previous connection is secure.
  25. Bend flat the twisted connection.
    Fig 12: Identifying I/P Module Twisted Connection
    GM263008Courtesy of GENERAL MOTORS CORP.
  26. Secure and insulate the connection using electrical tape.
  27. Twist together, bend, and tape the remaining connector wire lead to the remaining deployment wire.
    Fig 13: View Of Dual Insulated Connector Wires
    GM263012Courtesy of GENERAL MOTORS CORP.
  28. Connect the deployment harness to the I/P module connector.
    Fig 14: View Of Inflatable Restraint I/P Module Inline Connector
    GM202118Courtesy of GENERAL MOTORS CORP.
  29. Route the deployment harness out of the passenger side of the vehicle.
  30. Disconnect the inflatable restraint side impact module - LF connector (1), located under the driver seat.
    Fig 15: View Of Deployment Harness At Side Impact Module
    GM628320Courtesy of GENERAL MOTORS CORP.
  31. Cut the side impact module - LF connector out of the vehicle, leaving at least 16 cm (6 in) of wire at the connector.
  32. Strip 13 mm (0.5 in) of insulation from each of the connector wire leads.
    Fig 16: Identifying Proper Stripping Of Connection Wire Leads
    GM68649Courtesy of GENERAL MOTORS CORP.
  33. Cut two 4.6 m (15 ft) deployment wires from a 0.8 mm (18 gage) or thicker multi-strand wire. These wires will be used for the side impact module - LF deployment harness.
    Fig 17: Deployment Wires
    GM39390Courtesy of GENERAL MOTORS CORP.
  34. Strip 13 mm (0.5 in) of insulation from both ends of these wires.
  35. Twist together one end from each of the wires in order to short the wires. Deployment wires shall remain shorted, and not connected to a power source until you are ready to deploy the inflator module.
  36. Twist together one connector wire lead to one deployment wire.
    Fig 18: View Of Proper Twisting Of Connector Wire Lead To Deployment Wire
    GM68652Courtesy of GENERAL MOTORS CORP.
  37. Inspect that the previous connection is secure.
  38. Bend flat the twisted connection.
  39. Secure and insulate the connection using electrical tape.
    Fig 19: Bending Twisted Connection Flat & Insulating With Tape
    GM68660Courtesy of GENERAL MOTORS CORP.
  40. Twist together, bend, and tape the remaining connector wire lead to the remaining deployment wire.
    Fig 20: Taping Remaining Connector Wire Lead To Remaining Deployment Wire
    GM68662Courtesy of GENERAL MOTORS CORP.
  41. Connect the deployment harness to the side impact module - LF connector (1).
    Fig 21: View Of Deployment Harness At Side Impact Module
    GM628320Courtesy of GENERAL MOTORS CORP.
  42. Route the deployment harness out of the driver side of the vehicle.
  43. Disconnect the inflatable restraint side impact module - RF connector (1), located under the passenger seat.
    Fig 22: Locating Inflatable Restraint Side Impact Module - RF Connector
    GM628324Courtesy of GENERAL MOTORS CORP.
  44. Cut the side impact module - RF connector out of the vehicle, leaving at least 16 cm (6 in) of wire at the connector.
  45. Strip 13 mm (0.5 in) of insulation from each of the connector wire leads.
    Fig 23: Identifying Proper Stripping Of Connection Wire Leads
    GM68649Courtesy of GENERAL MOTORS CORP.
  46. Cut two 4.6 m (15 ft) deployment wires from a 0.8 mm (18 gage) or thicker multi-strand wire. These wires will be used for the side impact module - RF deployment harness.
    Fig 24: Deployment Wires
    GM39390Courtesy of GENERAL MOTORS CORP.
  47. Strip 13 mm (0.5 in) of insulation from both ends of these wires.
  48. Twist together one end from each of the wires in order to short the wires. Deployment wires shall remain shorted, and not connected to a power source until you are ready to deploy the inflator module.
  49. Twist together one connector wire lead to one deployment wire.
    Fig 25: View Of Proper Twisting Of Connector Wire Lead To Deployment Wire
    GM68652Courtesy of GENERAL MOTORS CORP.
  50. Inspect that the previous connection is secure.
  51. Bend flat the twisted connection.
  52. Secure and insulate the connection using electrical tape.
    Fig 26: Bending Twisted Connection Flat & Insulating With Tape
    GM68660Courtesy of GENERAL MOTORS CORP.
  53. Twist together, bend, and tape the remaining connector wire lead to the remaining deployment wire.
    Fig 27: Taping Remaining Connector Wire Lead To Remaining Deployment Wire
    GM68662Courtesy of GENERAL MOTORS CORP.
  54. Connect the deployment harness to the side impact module - RF connector (1).
    Fig 28: Locating Inflatable Restraint Side Impact Module - RF Connector
    GM628324Courtesy of GENERAL MOTORS CORP.
  55. Route the deployment harness out of the passenger side of the vehicle.
  56. Completely cover the windshield and the front door openings with a drop cloth.
  57. Deploy each deployment loop one at a time.
  58. Stretch out all of the deployment harness wires on the left and right side of the vehicle to their full length.
    IMPORTANT: The inflator module will deploy when the wire ends contact the power source.
  59. Place a power source, 12 V minimum A minimum, such as a vehicle battery, near the shorted end of the harnesses.
  60. Separate one set of wires and touch the wire ends to the power source in order to deploy the inflator modules.
  61. Disconnect the deployment harness from the power source and twist the wire ends together.
  62. Continue the same process with the remaining deployment harnesses that are available.
  63. Remove the drop cloth from the vehicle.
  64. Disconnect all harnesses from the vehicle.
  65. Discard the harnesses.
  66. Scrap the vehicle in the same manner as a non-SIR equipped vehicle.
  67. If one or more of the inflator modules did not deploy, perform the following steps to remove the undeployed modules from the vehicle:
  68. Call the Technical Assistance Group for further assistance.