Installing coolant pumps
WARNING: This page is about a different car, the 2022 BMW X7, 2021 BMW X7, 2020 BMW X7, and 2019 BMW X7. However, it is still accessible from the selected car via links, so may be relevant.
TIGHTENING TORQUES SPECIFICATION
| Coolant pump to component carrier | ||
|---|---|---|
| M6x20 | tightening torque | 10.5 Nm |
- Replace sealing ring (1).
Parts: Sealing ring
- Feed in and install coolant line (2).
- Tighten down screw (1).
TIGHTENING TORQUES SPECIFICATION
| Coolant line of coolant radiator to coolant pump | ||
|---|---|---|
| M6x20 | tightening torque | 10.5 Nm |
Follow-up work
- Refer to INSTALLING THE COOLANT LINE BETWEEN THE CYLINDER HEAD AND THE COOLANT PUMP .
- Refer to INSTALLING THE DRIVE BELT FOR ALTERNATOR .
- Refer to CONNECTING THE COOLANT LINE TO THE HIGH-TEMPERATURE COOLANT RADIATOR .
- Refer to INSTALLING CHARGE AIR LINE .
- Refer to INSTALLING THE CLEAN AIR PIPE AND THE RESONATOR .
- Refer to INSTALLING THE INTAKE FILTER HOUSING (TENSION STRUT REMOVED ON SHOCK TOWER) .
- Refer to INSTALLING FAN COWL .
- Refer to INSTALLING THE REAR TOP CROSS CONNECTION .
- Refer to INSTALLING TENSION STRUT ON LEFT AND RIGHT SHOCK TOWER .
- Refer to INSTALLING UPPER CROSS CONNECTION .
- Refer to INSTALLING THE COVER IN THE ENGINE COMPARTMENT AT TOP LEFT AND RIGHT .
- Refer to FILLING THE COOLING SYSTEM WITH THE VACUUM FILLING UNIT .
- Refer to VENTING THE HIGH-TEMPERATURE COOLANT SYSTEM .
- Refer to CHECKING COOLING SYSTEM FOR WATERTIGHTNESS .
- Refer to INSTALLING ACOUSTIC COVER .
- Refer to INSTALLING THE FRONT BOTTOM RIGHT WHEEL ARCH COVER .
- Refer to INSTALLING FRONT UNDERBODY PROTECTION .