Installing the high-pressure line between the high-pressure pump and the high-pressure rail
- Guide in the high pressure line (4) in the mount (3) and install.
- Tighten the union nuts (arrows) with the special tool 0 495 280 (13 0 140).
TIGHTENING TORQUE SPECIFICATIONS
| High pressure line between the rail and the high pressure pump | ||
|---|---|---|
| M14x1.5 | tightening torque | 33 Nm |
- Feed in and install wiring harness section of the engine wiring harness (4).
The locks (3) must engage audibly.
- Connect connectors (1) and (2) and lock.
The connectors (1) and (2) must audibly engage.
Follow-up work
- Refer to INSTALLING ALL IGNITION COILS .
- Refer to MOUNTING THE SERVICE OPENING IN THE SOUND INSULATION ON TOP OF THE ENGINE .
- Refer to INSTALLING ACOUSTIC COVER .
- Refer to CONNECTING ALL BATTERY GROUND LEADS .
- Refer to RESET ULTRA-SMALL QUANTITY ADAPTATION .