Installing the blow-off valve of cylinder bank 2
- Check the seal (1) for damage. If necessary, replace the blow-off valve (2).
Parts: Blow-off valve
- Position the blow-off valve of cylinder bank 2.
- Position all screws manually.
- Tighten screw.
TIGHTENING TORQUE SPECIFICATIONS
| Blow-off valve to turbocharger | ||
|---|---|---|
| M6 | tightening torque | 9±1 Nm |
- Tighten screw.
TIGHTENING TORQUE SPECIFICATIONS
| Blow-off valve to turbocharger | ||
|---|---|---|
| M6 | tightening torque | 9±1 Nm |
- Tighten screw.
TIGHTENING TORQUE SPECIFICATIONS
| Blow-off valve to turbocharger | ||
|---|---|---|
| M6 | tightening torque | 9±1 Nm |
- Connect connectors (1) and lock.
Follow-up work
- Refer to INSTALLING THE CLEAN AIR PIPE OF CYLINDER BANK 2 .
- Refer to CONNECTING THE LEFT CHARGE AIR LINE TO THE TURBOCHARGER .
- Refer to INSTALLING THE COVER OF THE LEFT DME CONTROL UNIT .
- Refer to INSTALLING ACOUSTIC COVER .