Install the transfer box (ATC 13-1)
- Lightly grease the gearing (1) in the transfer box (VTG) and the gearing (2) of the automatic transmission.CONSUMABLE SPECIFICATION
Ball bearing grease 100 g, Tube 81229407174 - Replace the O-ring (1) before installing the front prop shaft in the transfer box (VTG).
Parts: O-ring
- Apply a thin coat of grease to the gearing of the output flange in the transfer box (VTG).CONSUMABLE SPECIFICATION
Ball bearing grease 100 g, Tube 81229407174 - Position the transfer box (VTG) with the help of a support person.
- Position the front prop shaft (1) on the output flange (3) of the transfer box (VTG).
- Align the front prop shaft (1) with the help of the marks (2) and (4).
- Install the transfer box (VTG) and, at the same time, slide the front prop shaft (1) into the output flange (3) of the transfer box (VTG).
- Remove any leaked grease on the prop shaft.NOTE: TECHNICAL INFORMATION
When assembling, it is essential to observe screwing sequences and tightening torques.
Failure to comply with the regulations can lead to leaks and damage. - Tighten the screws in order from (1) to (5).TIGHTENING TORQUE SPECIFICATION
Transfer box to automatic transmission M10 tightening torque 43 Nm - Connect the connector (1) on the VTG control unit (longitudinal torque distribution) (2).
- Install the ground strap (2).
- Tighten down screw (1).TIGHTENING TORQUE SPECIFICATION
Ground strap to transmission or body M8 tightening torque 19 Nm
Follow-up work
- Refer to INSTALLING THE RUBBER MOUNT FOR THE TRANSMISSION BEARING (ALL-WHEEL DRIVE) .
- Refer to INSTALLING TRANSMISSION CROSS MEMBER .
- Refer to FASTENING THE PROP SHAFT (PARTIALLY REMOVED) .
- Refer to INSTALLING THE HEAT SHIELD .
- Refer to INSTALLING THE COMPLETE EXHAUST SYSTEM .
- Refer to INSTALLING THE CONNECTING SUPPORTS ON THE TUNNEL .
- Refer to RECONNECTING ALL BATTERY GROUND LEADS .
- Refer to CHECKING/TOPPING UP THE TRANSFER BOX OIL (ACTIVE TORQUE CONTROL 13-1) .
- Refer to INSTALLING UNDERBODY PROTECTION AT REAR .
- Refer to INSTALLING THE CENTER UNDERBODY PROTECTION .
- Refer to ACTIVATING THE 48 V ELECTRICAL SYSTEM .