Installing the 48V battery
tightening torque specification
| Battery tray to body | ||
|---|---|---|
| M8 screw | Tightening torque | 19 nm |
tightening torque specification
| Battery tray to body | ||
|---|---|---|
| M6 screw | Tightening torque | 8 nm |
- Install cover caps (1) by turning.
- Check the seals of the coolant flange for damage, replace if necessary.
- Position the coolant connection.
- Tighten down screw (3).
tightening torque specification
| Coolant flange screw | ||
|---|---|---|
| Screw M6x20 | Tightening torque | 8 nm |
- Remove disconnection tool (2) from the coolant lines (1).
WARNING:
Incorrect screw connection of the positive battery cable.
Risk of fire!
Risk of fire!
- Ensure that the positive battery cable is screwed with the Correct nut.
- Position battery positive cable (2) on the 48V battery (3).
- Tighten nut on positive battery cable (2).
tightening torque specification
| Positive battery cable to 48V battery | ||
|---|---|---|
| Nut M8 | Tightening torque | 19 nm |
Follow-up work
- Refer to CONNECTING THE COOLANT LINES FOR THE LOW-TEMPERATURE COOLANT CIRCUIT .
- Refer to FILLING THE LOW-TEMPERATURE COOLING SYSTEM WITH THE VACUUM FILLING EQUIPMENT .
- Refer to INSTALLING INTAKE FILTER HOUSING .
- Refer to INSTALLING THE RIGHT FRONT-END STRUT .
- Refer to INSTALLING ACOUSTIC COVER .
- Refer to INSTALLING TENSION STRUT ON SHOCK TOWER .
- Refer to INSTALLING WINDSHIELD PANEL COVER .
- Refer to INSTALLING LEFT AND RIGHT WIPER ARM .
- Refer to INSTALLING THE COVER OF THE ENGINE COMPARTMENT ON THE REAR LEFT .
- Refer to CONNECTING ALL BATTERY GROUND LEADS .
- Refer to ACTIVATING THE 48V ELECTRICAL SYSTEM .