41 14 502 Replacing Rear Left Outer Wheel Arch Section (Rear Left Side Panel Removed)

WARNING: This page is about a different car, the 2013 BMW X5, 2012 BMW X5, and 2011 BMW X5. However, it is still accessible from the selected car via links, so may be relevant.

Read contents of SAFETY INFORMATION  and BODY, GENERAL .

Spot-weld bonding is used on this vehicle. Observe specific PROCEDURE .

Remove or cover those vehicle components in the repair area which are susceptible to heat or dust.

Use only approved SPOT-WELDING APPARATUS  for repairs!

The following new body parts are required:

Mark severance cuts in accordance with specified measurements and cut.

IMPORTANT: Cut outer metal sheet only.

measurement "a" =70 mm below 15 mm dia. bore

measurement "b" = 130 mm

Installation: 

Weld in REINFORCEMENT PLATES  at severance cuts.

Fig 2: Identifying Cutting Dimensions
G04791210Courtesy of BMW OF NORTH AMERICA, INC.

Open weld joints in areas (1).

IMPORTANT: Burn hazard!

Remove cavity acoustic baffles in area (3).

Installation:

Apply window glass adhesive to CAVITY ACOUSTIC BAFFLE  (2).

Make cavity acoustic baffle (3) with CAVITY FOAM .

Fig 3: Identifying Cavity Acoustic Baffles And Weld Joints Area
G04791222Courtesy of BMW OF NORTH AMERICA, INC.

Mark severance cut (1) in accordance with measurement and cut.

IMPORTANT: Cut outer metal sheet only.

Dimension "a" = 20 mm

Open weld joints in area (2).

Fig 4: Identifying Cutting Dimension And Weld Joints Area
G04791223Courtesy of BMW OF NORTH AMERICA, INC.

Remove CAVITY ACOUSTIC BAFFLE .

Mark severance cut in accordance with specified measurement and cut.

Measurement "a" = 20 mm distance from radius

Fig 5: Identifying Cutting Dimension
G04791224Courtesy of BMW OF NORTH AMERICA, INC.

Cut wheel arch along line (1).

Open weld joints in area (2).

Installation: 

Weld new part in area (3) overlapping with wheel arch.

Fig 6: Cutting Wheel Arch, Opening Weld Joints, And Welding New Part
G04791225Courtesy of BMW OF NORTH AMERICA, INC.

Preparation of new part: 

Mark new part in accordance with severance cut on vehicle + 20 mm extra material and cut (1).

Fig 7: Identifying Cutting Line
G04791226Courtesy of BMW OF NORTH AMERICA, INC.