Preparing New Part
NOTE:
TECHNICAL INFORMATION
Structural adhesive bonding.
Observe preparation of bonding surfaces.
For additional information see: 41 00... BMW bonding instructions
Structural adhesive bonding.
Observe preparation of bonding surfaces.
For additional information see: 41 00... BMW bonding instructions
- Release the bonded rivet connections in the areas (1)
. Remove connecting plate (2)
.
- Remove adhesive residue from bonding surfaces.
- Seal the hole (1) by MAG weld.
- Drill out holes (2)
to dia. 6.8 mm.
- Adjust new parts to fit with alignment bracket or universal fixture and secure.
- Prepare the reinforcement (1)
in the area (2)
for joining by welding.
- Prepare the areas (1) through (4) for structural adhesive bonding of steel to steel and steel to aluminum.
- In the areas (1) and (2) , drill out the holes to Ø 6.8 mm and transfer to the new part.
- In the area (3) , drill out holes to Ø 6.8 mm and transfer to both new parts.
- In the area (4)
, drill out holes to Ø 6.8 mm. Number and position analogous to the flow-drill screws from series production.
- Prepare areas (1) for structural adhesive bonding of steel to aluminum.
- In areas (1)
, drill out holes to Ø 6.8 mm and transfer to the new part.
- Prepare areas (1) and (2) for structural adhesive bonding of steel to aluminum.
- In areas (1)
and (2)
, transfer the holes from the wheel well to the strut tower. Drill out holes to dia. 6.8 mm.
- Prepare areas (1) for structural adhesive bonding of steel to aluminum.
- Transfer the holes from the engine compartment bulkhead to the strut tower in the areas (1)
. Drill out holes to dia. 6.8 mm.NOTE: TECHNICAL INFORMATION
For additional information see: 41 00... Spot-weld bonding steel components - Adjust the new part (1) and prepare it for joining by welding in the areas (2) and (3) .
- In areas (3)
, observe the procedure when replacing spot-welded adhesive joints for series production.
- Prepare areas (1)
and separating cuts (2)
for joining by welding.NOTE: TECHNICAL INFORMATION
For additional information see: 41 00... Spot-weld bonding steel components - In the area (1) , observe the procedure when replacing spot-welded adhesive joints from series production.
- Prepare areas (3)
and (4)
for structural adhesive bonding of steel to aluminum.
- In the areas (3) , drill cylinder bores of Ø 6.8 mm on new parts, similar to series production.
- In area (4) , set a bore of Ø 6.8 mm for blind rivet.
- Prepare the areas (1) and (2) for joining by welding.
- In areas (2) , observe the procedure when replacing spot-welded adhesive joints for series production.
Note the bonded rivet connections in the areas (3) .
Check ground pins and replace if necessary
NOTE:
Schematic diagram is for example purposes. Some parts may differ in certain details.
- Check the ground pins (1) for stability and renew if necessary.