WARNING: This page is about a different car, the 2011 BMW 750xi, 2011 BMW 750Lxi, 2010 BMW 750xi, and 2010 BMW 750Lxi. However, it is still accessible from the selected car via links, so may be relevant.
IMPORTANT: Do not move vehicle with driving power once propeller shaft has been removed.
Replace output flange only  together with a new radial shaft seal.
After completion of work, check GEARBOX OIL LEVEL .
Use only the APPROVED OIL .
Failure to comply with this requirement will result in serious damage to the transfer box!

Operation is identical to REPLACING RADIAL SHAFT SEAL FOR OUTPUT TO THE FRONT AXLE .