17 11... Bleed and fill the cooling system for the charge air cooler with the vacuum filling unit: Application
Connect filling unit (1) with a suitable adapter (2) from special tool set 17 0 100 to the charge air cooler expansion tank.
Shutoff valves (A) and (B) must be closed.
Connect venturi nozzle (1) to filling unit (2).
Connect compressed air (1) and open shutoff valve (B).
The venturi nozzle produces a flow noise.
Then open shutoff valve (A) until the filling hose (1) is free of bubbles. Close shutoff valve (A) again. The filling hose (1) is vented in this way.
Shutoff valve (B) remains open. Generate vacuum in cooling cycle for approx. 1 minute. The end vacuum is reached at a vacuum of -0.7 to -0.95 bar. Green scale on the vacuum meter.
Then close shutoff valve (B) again.
Both shutoff valves (A) and (B) must be closed.
Then seal Venturi nozzle (1).
The cooling system must hold the vacuum for 30 seconds. If the needle in the vacuum meter falls, this indicates a leak in the cooling system.
If the vacuum remains constant, proceed with filling.
In the event of a leak, check the cooling system for the charge air cooler for leaks.
Position the filling unit container at the same height as the coolant expansion tank.
Shut-off valve (B) remains closed during the filling process.
To fill the cooling system, open shutoff valve (A) to filling unit container.
Coolant is now added.
The filling procedure is finished when the needle in the vacuum meter is at 0 bar or no longer falls.
If necessary, reduce remaining vacuum. Open shutoff valve (B) to do so.
Remove filling unit with adapter from expansion tank.
Close charge air cooler expansion tank.
Adjust coolant level to maximum.
Check cooling system for charge air cooler for leaks.