51 48... Notes for bonding sound insulation (SI), doors
WARNING: This page is about a different car, the 2010 BMW X6. However, it is still accessible from the selected car via links, so may be relevant.
Special tools required:
IMPORTANT:
Do not pull on the sound insulation in jerks (risk of damage)
General:
Sound insulation is bonded to the inner door panel.
Bonded sound insulation must not be subjected to load (e.g. leak test) before 5 hours have elapsed.
On-the-job safety:
When working with bonding products (adhesive, cleaning agent, etc.):
- Wear safety goggles, protective gloves and if necessary an apron.
- Ensure rooms are well ventilated.
- Change work clothing contaminated with adhesive immediately.
- Change work clothing contaminated with solvents and swelling agents immediately (keep spare work clothing on hand).
- Take skin protection measures, provide washing facilities including hot water, use silicone-free skin creams
- Provide eye douche facilities, change water regularly (once a month).
- Comply with the relevant safety regulations
Handling adhesive area on inner door panel:
| Adhesive | Cleaning |
|---|---|
| a. Butyl bead applied to sound insulation with protective film | a. CLEANING AGENTR2 Under no circumstances: paint thinning |
| b. Butyl mini-round profile Ø 3 mm from the roller | b. Carry out bonding only after an air drying time ≥ 1 min. Air drying time may be omitted if the entire bonding surface is wiped with a dry cloth |
| c. Butyl round profile Ø 6 mm from the roller | c. After cleaning, the bonding surface may not be touched with hands or fouled again |
Repair in area of sound insulation, door:
| Repair in the event of damaged sound insulation or leakage |
|
The sound insulation must be bonded watertight below the door lock:
- Flat bonding surface required all round
- No bonding in event of moisture (e.g. condensation, etc.)
- Bonding area must not show any traces of adhesion-reducing residues (e.g. separating agents, greases, oils, paraffins, plastisols, cavity wax, polishing dust residues, etc.)
- Remove the protective film directly before joining (under no circumstances remove earlier, since the butyl, because of its stickiness, will very quickly pick up adhesion-reducing dirt contaminants)
- The sound insulation must be attached with positional accuracy to the inner door panel, because it is no longer possible to change the position without damaging the butyl bead
- With repainted areas, the maximum permitted temperature of 90°C may not be exceeded in the area of the sound insulation. Otherwise, the sound insulation must be removed (and replaced, if necessary).
Expiry date of adhesive:
24 months, see label on packaging
Disposal of the cleaning cloth:
Cleaning cloths and cleaning agent residues are hazardous waste (see also safety data sheet)
Disposal of adhesive:
Hazardous waste (see also safety data sheet)