64 51... Leak-testing condenser
Special tools required: 00 9 030, 64 5 121, 64 5 122, 64 5 123
Necessary preliminary tasks: Drain off air conditioning system . Detach refrigerant lines from condenser. Tightening torque 64 53 6AZ .
Fit and secure sealing adapter 64 5 123 to connection of low-pressure line. Fit and secure test adapter 64 5 122 to connection of high-pressure line. Tightening torque 64 53 6AZ .
Connect special tool 64 5 122 to special tool 64 5 121.
Connect nitrogen pressure bottle with pressure reducer to pressure gauge and then connect to special tool 64 5 121 (connecting hose).
- Testing apparatus must be leakproof.
- Ambient temperature and temperature of vehicle must not change during the test procedure.
- Do not move the vehicle during this period
Apply test pressure of 10 bar slowly and close nitrogen pressure bottle. Check leak-tightness of testing apparatus and of connection to refrigerant line. Set test pressure of 10 bar is only permitted to drop by 2 bar to 8.5 bar over a test period of 1.5 hours. If the pressure loss is greater than 1.5 bar, this indicates that there is a leak in the condenser unit.
After leak-testing:
Replace sealing rings. Use special tool 00 9 030 to mount sealing rings without damaging them.
Assemble A/C system
Evacuate and fill A/C system