11 00 590 Replacement Power Plant (N54)
WARNING: This page is about a different car, the 2010 BMW 135i, 2009 BMW 135i, and 2008 BMW 135i. However, it is still accessible from the selected car via links, so may be relevant.
Necessary preliminary tasks:
- Remove and install engine . See 11 00 050 REMOVING AND INSTALLING ENGINE (N54) .
- Mount engine on assembly stand . See 11 00 MOUNTING ENGINE ON ASSEMBLY STAND (N54) .
- If necessary, remove foreign bodies from turbocharger group.
- Check all assemblies and convert to replacement power plant.
Remove transportation locks (1).
NOTE:
Catch escaping engine oil with a suitable cloth (2).
Transportation locks (1) are no longer needed.
Modify screw plugs (1) from old power plant.
Insert screw plugs (1).
Tightening torque. See 11 42 11AZ in 11 42 OIL FILTER AND PIPES .
Secure oil cooler lines with mounting bar (2).
Assemble engine.