Front Coolant Pipe, Removing And Installing, 2.9L Engine: Installing
Install in the reverse order of removal while noting the following:
- Replace the seal and O-ring after removal.
- Secure all hose connections with hose clamps that match the ones used in series production. Refer to the Electronic Parts Information (ETKA).
- Used coolant cannot be used again.
-- Coat the O-ring and seal with coolant and install them.
-- Press on the seal all the way onto the coolant pipe.
-- Install the ribbed belt. Refer to RIBBED BELT, REMOVING AND INSTALLING .
-- If removed, install the upper air duct pipe. Refer to AIR DUCT PIPE, REMOVING AND INSTALLING, WITH RADIATOR INSTALLED 2.9L ENGINE .
-- Fill the coolant. Refer to COOLANT, DRAINING AND FILLING, 2.9L ENGINE .