Thermal Management Coolant Temperature Sensor 8 -G968-, REMOVING AND INSTALLING, AUDI Q5
Shop Crane - Drip Tray:VAS 6208
Procedure
- High-voltage system cold.
-- To remove any residual pressure in the cooling system, cut the seal tab -3- and open the coolant expansion tank cap -1- for the high-voltage system cooling circuit.
-- Disconnect the connector -1-.
Collecting coolant and determining volumes.
-- Place the Shop Crane - Drip Tray:VAS 6208 underneath.
-- Remove the bolt -2-, and remove the Thermal Management Coolant Temperature Sensor 8 -G968-.
- Allocation of the O-ring/centering ring. Refer to Figure.
-- To prevent coolant loss, install the new coolant temperature sensor immediately.
-- Add the coolant. Refer to COOLANT, ADDING AND COOLING SYSTEM, BLEEDING, HIGH-VOLTAGE SYSTEM COOLING CIRCUIT .
-- Drain and fill the coolant for the high-voltage system cooling circuit only if the coolant loss is greater than 500 ml. Refer to COOLANT, DRAINING, HIGH-VOLTAGE COOLING CIRCUIT and Refer to COOLING SYSTEM, FILLING, HIGH-VOLTAGE SYSTEM COOLING CIRCUIT .
Tightening Specifications