Home >> Audi >> 2017 >> A7 Quattro Competition >> Repair and Diagnosis >> External Pages >> Different car >> Section 88 (Final Drive & Differential - S TRONIC Transmission Internal Components) >> 39 Final Drive, Differential >> Differential >> Left Flange Shaft Ball Bearing Pre-Tension, Checking And Adjusting >> Pre-Tension On Ball Bearing, Adjusting, Left Flange Shaft >> Notes

Pre-Tension On Ball Bearing, Adjusting, Left Flange Shaft: Notes

WARNING: This page is about a different car, the 2015 Audi S7, 2015 Audi RS 7, 2014 Audi S7, 2014 Audi RS 7, and 2013 Audi S7. However, it is still accessible from the selected car via links, so may be relevant.
NOTE:

the pre-tension on the left flange shaft ball bearing must be optimized only on certain vehicles, refer to the table for a list of the vehicles, refer to Installing => .

This is not necessary on vehicles built later because they have been redesigned.

Procedure 

Fig 2: Identifying Contact Surface
GWWA39-10527Courtesy of AUDI OF AMERICA, LLC

-- Clean off any dirt and corrosion from the contact surface -arrow- using 150 grain sand paper.

NOTE:

It is not necessary to sand the contact surfaces all the way down to bare metal. It is enough to just remove any dirt and corrosion.

-- Clean the contact surface and bearing seat.

-- Install the new left flange shaft ball bearing -arrow- into the bearing seat.

Fig 3: Left Flange Shaft Ball Bearing
GWWA39-10528Courtesy of AUDI OF AMERICA, LLC

Next procedure: