Evaporative Emission (EVAP) Canister Purge Regulator Valve N80 , Checking
Special tools, testers and auxiliary items required
- Multimeter.
- Wiring diagram.
Test requirements
- The Evaporative Emission (EVAP) Canister Purge Regulator Valve N80 fuse OK.
- The ignition switched off.
- Voltage for the Evaporative Emission (EVAP) Canister Purge Regulator Valve N80 is supplied via the Engine Component Power Supply Relay J757.
Test procedure
- Perform a preliminary check to verify the customers complaint. Refer to → General Diagnosis .
Start diagnosis
- Remove the rear engine cover - arrows -.
- Disconnect the Evaporative Emission (EVAP) Canister Purge Regulator Valve N80 electrical harness connector - 3 -.
Checking internal resistance
- Using a Multimeter , check the Evaporative Emission (EVAP) Canister Purge Regulator Valve N80 terminals 1 and 2 for resistance.
Specified value: 22,0 to 30,0 Ω.
Engine Component Power Supply Relay J757
- Replace the Evaporative Emission (EVAP) Canister Purge Regulator Valve N80.
If the specification is obtained:
Checking voltage supply
- Using a Multimeter , check the electrical harness connector terminal 1 to 2 for voltage.
- Operate the starter briefly.
Specified value: battery voltage.
If the specified value was not obtained:
- Using a Multimeter , check the electrical harness connector terminal 1 to Ground (GND) for voltage.
| Evaporative Emission (EVAP) Canister Purge Regulator Valve N80 electrical harness connector terminal | Measure to |
|---|---|
| 1 | Engine Ground (GND) |
- Operate the starter briefly.
Specified value: battery voltage.
If the specified value is not obtained:
- Check the wiring connection from the electrical harness connector terminal 1 to the Engine Component Power Supply Relay J757 terminal 2/87 for an open circuit or short to Ground (GND).
- Check the electrical harness connector for damage, corrosion, lose or broken terminals.
- If necessary, repair the wiring connection.
If the specified value was obtained:
Check Ground (GND) activation
If the manufacturers test box is being used. Perform the following step.
- Install the test box. Refer to → 24 - FUEL INJECTION SYSTEM .
If the manufacturers test box is not being used. Perform the following step.
- Remove the Engine Control Module (ECM) J623. Refer to → Engine Control Module (ECM) J623 , Removing and Installing .
- Using a Multimeter , check the Evaporative Emission (EVAP) Canister Purge Regulator Valve N80 electrical connector terminal 2 to Engine Control Module (ECM) J623 electrical connector T94 terminal 49 for an open circuit.
| Evaporative Emission (EVAP) Canister Purge Regulator Valve N80 electrical harness connector terminal | Engine Control Module (ECM) J623 electrical connector T60 terminal test box socket |
|---|---|
| 2 | 49 |
Specified value: 1.5 Ω max.
If the specification is not obtained:
- Check the wiring for a short circuit to Battery positive (+), Ground (GND) or an open circuit.
- Check the electrical harness connector for damage, corrosion, lose or broken terminals.
- If necessary, repair the wiring connection.
If the specification was obtained:
- Replace the Engine Control Module (ECM) J623. Refer to → Engine Control Module (ECM) J623 , Removing and Installing .
- Install the rear engine cover - arrows -.
Final procedures
After the repair work, the following work steps must be performed in the following sequence:
- Check the DTC memory.
- If necessary, erase the DTC memory. Refer to Diagnostic Mode 04: Reset/delete Diagnostic Data .
- If the DTC memory was erased, generate readiness code. Refer to Readiness Code .
- End of diagnosis.