LEMON Manuals: Even more car manuals for everyone
Home >> Audi >> 2011 >> Q5 2.0T >> Repair and Diagnosis >> External Pages >> Different car >> Section 1571 (Turbocharger, Supercharger [CNRB]) >> 21 Turbocharger, Supercharger >> Turbocharger >> Turbocharger, Removing And Installing >> Installing

Turbocharger, Removing And Installing: Installing

WARNING: This page is about a different car, the 2014 Volkswagen Touareg and 2013 Volkswagen Touareg. However, it is still accessible from the selected car via links, so may be relevant.

Further installation is performed in reverse order of removal, while noting the following:

NOTE:

Secure all hose connections with hose clamps that match the ones used in series production. Refer to the Parts Information.

To ensure the turbocharger is supplied with enough oil, let the engine run at idle for about one minute after installing the turbocharger. Do not increase the engine speed during this time.

-- Replace the seals and O-rings.

-- Fill the turbocharger with engine oil at the connection for oil supply line.

-- Connections and wire routing. Refer to the appropriate Wiring Diagram.